AMEC
Berca Indonesia (ABI), AMEC's joint venture company with
CCM Group, has won a $1m oil and gas engineering design contract on
TotalE&P Indonesie's Tunu Phase 11 development.
ABI will be responsible for detailed engineering work, including pre-engineering, survey, detailed engineering and final documentation for a new utility platform for the Tunu shallow-water gas field in the Mahakam Delta, East Kalimantan.
The contract has been awarded by PT Punj Lloyd Indonesia, Total's engineering, procurement and construction contractor for the platform.
The work is scheduled to be completed in September 2007, with the platform due to commence operation in mid-2008.