Saudi Electricity commissions ABB substation
ABB has won an order worth $89m (£59m) from Saudi Electricity, Saudi Arabia’s national power-transmission and distribution provider, to build a substation to ensure reliable power supplies for the King Abdullah Financial District in the city of Riyadh.

The substation will be close to the financial centre and feed four smaller substations situated within the district. The project is expected to be completed in around 22 months.
ABB is responsible for the turnkey delivery of a 380/132/13.8kV substation and will design, supply, install and commission the installation, as well as carry out the civil works. Key products to be supplied include the gas-insulated switchgear (GIS), transformers, medium-voltage switchgear and cables.
The substation will be equipped with an IEC 61850 compliant automation, control and protection system. IEC 61850 is an international communications standard that ensures interoperability and open communications between substation devices and other grid installations.
The King Abdullah financial district will host the headquarters of the country’s Capital Market Authority, the Saudi Stock Exchange, and several banks and financial institutions.
Register now to continue reading
Thanks for visiting The Engineer. You’ve now reached your monthly limit of news stories. Register for free to unlock unlimited access to all of our news coverage, as well as premium content including opinion, in-depth features and special reports.
Benefits of registering
-
In-depth insights and coverage of key emerging trends
-
Unrestricted access to special reports throughout the year
-
Daily technology news delivered straight to your inbox
Radio wave weapon knocks out drone swarms
Probably. A radio-controlled drone cannot be completely shielded to RF, else you´d lose the ability to control it. The fibre optical cable removes...