Alstom has won a €250 million contract from TRUenergy, a subsidiary of CLP, to supply a turnkey 400MW gas-fired combined cycle power plant in
Alstom will design, supply, install and commission the entire power plant, consisting of a GT26 gas turbine, a 160MW steam turbine, condenser, heat recovery steam generator, step-up transformer, plant control systems, civil works and the remaining plant.
The project is located at
Alstom was previously awarded two similar EPC (engineering, procurement and construction) contracts in 2005 for the 450MW Braemar Power Project in