The German technology group Linde has secured its largest individual order ever for air separation plants in
The two oxygen production facilities have been commissioned by National Industrial Gas Company (NIGC), the largest industrial gases company in the
Linde will assume responsibility for the engineering, procurement of equipment and materials as well as construction and commissioning of the facilities, each of which will generate 3,000 tonnes of oxygen per day.
The plants are scheduled to start operation in April 2008.